THE WORKED REVIEW / BASED ON THE ORIGINAL RECORDS
The current detail is 8 mm short in clear width.
Width704 − 16 − 16 = 672 mm680 mm minimum → 8 mm short
Height900 − 30 − 30 = 840 mm820 mm minimum → 20 mm above minimum
Both dimensions must be met. Extra height does not offset insufficient width. The supplier’s consumptions include seals, latch keepers and all inward throat projections. This establishes a dimensional conflict in the scheduled package, not an installed fit test. R02 · p. 1, §§1–2 ↗ R06 · p. 1, §2 ↗
The supplier accepted a different configuration.
TD-27-09 accepts SJ-16 jambs on the 720 × 900 mm cutout in CL-207 Rev B. That combination gives 720 − 16 − 16 = 688 mm clear width and 900 − 30 − 30 = 840 mm clear height. Changed cutout dimensions must return for technical review. Referencing that decision does not establish acceptance of the current 704 × 900 mm cutout. R04 · p. 1, §§1–2 ↗ R06 · p. 1, §3 ↗
The final solution and joint layout remain unresolved.
The PM requires applicable supplier and architect reviews for a changed cutout or visible joint layout and records no disposition on the proposal. The current package lists architectural joint-layout review as pending. No corrective detail or tolerance is prescribed here. R05 · p. 1, §1 ↗ R06 · p. 1, §3 ↗
Working depth is a separate, unconfirmed check.
The survey measured 1295 mm from carrier datum C0 to the opposite finished wall. The required working depth is 1260 mm from the finished cladding face. With projection P unresolved, working depth = 1295 − P; meeting the minimum requires P ≤ 35 mm, subject to final site verification. This is a calculated limit, not an approved projection or demonstrated failure. The 738 × 920 mm carrier support opening is explicitly not the cladding cutout or frame throat. R02 · p. 1, §3 ↗ R03 · p. 1, §§1–3 ↗ R06 · p. 1, §3 ↗
Technical acceptance is not fabrication release.
R01 requires an item-specific written PM release. R05 permits only flitch matching and reservation of uncut stock; it issues no fabrication release and keeps CNC cutting and cassette assembly on hold pending interface resolution and written release. R06 says the release is not attached and calls its issue a detailing transmittal. No subsequent written release is in these supplied records. A reserved CNC slot is not permission to cut. R01 · p. 1, §3 ↗ R05 · p. 1, §§2–3 ↗ R06 · p. 1, §3 ↗
What a qualified practitioner needs to resolve
- Confirm the final cutout and frame consumptions; resolve the width conflict and obtain applicable supplier review.
- Resolve the revised joint layout; establish P and verify unobstructed working depth and tray withdrawal.
- Coordinate the production information with recorded decisions and confirm the required written PM release.
This exercise does not authorize cutting, assembly or fabrication.